Effectiveness Analysis of Milling Machine Using Overall Equipment Effectiveness and Determination of Preventive Maintenance Using Age Replacement
Analisa Efektivitas Mesin Milling Menggunakan Overall Equipment Effectiveness dan Penentuan Preventive Maintenance Menggunakan Age Replacement
DOI:
https://doi.org/10.21070/ups.1966Keywords:
Age Replacement, Milling Machine, Overall Equipment Effectiveness (OEE)Abstract
PT. INKA is a company engaged in the manufacturing of railroad cars. During the production process, there are often problems with machine damage. Based on company data from 2021 to 2022, milling machines are machines that have the most damage compared to other production machines, namely 43 times. The purpose of this study is to determine the effectiveness of the six milling machines and to determine preventive maintenance recommendations through preventive replacement of components. The method used is the Overall Equipment Effectiveness and Age Replacement methods. The results of research conducted on the six milling machines obtained OEE values for CNC Plano 133 of 84.20% and Horizontal Milling 142 of 83.96%, so these machines do not meet the ideal OEE value. Furthermore, it was found that the time interval for component replacement on the Plano 133 and Horizontal Milling 142 CNC machines was within 10 days.
Downloads
References
L. Irdiansyah and E. Ludiya, “Pemeliharaan Korektif Mesin Cetak Offset 4 Warna Pada Cv. Aries Anugrah Karya Utama,” J. Adm. Bisnis, vol. 18, no. 1, pp. 1–16, 2022, doi: 10.26593/jab.v18i1.5535.1-16.
S. A. Pratama, B. I. Putra, T. Industri, F. Sains, and U. M. Sidoarjo, “ANALYSIS OF MACHINE MAINTENANCE USING MARKOV,” Semin. Nas. Inov. Teknol., pp. 208–214, 2022.
M. A. dan A. Z. Sultan, Manajemen Perawatan, Pertama. Yogyakarta: Deepublish, 2018. [Online].
B. Fadhilah, P. Aulia, and A. J. Pratama, “Overall Equipment Effectiveness ( OEE ) Analysis to Minimize Six Big Losses in Continuous Blanking Machine,” IJIEM (Indonesian J. Ind. Eng. Manag., vol. 1, no. 1, pp. 25–32, 2020.
T. Rachman, D. N. Watunglawar, M. D. Amperajaya, S. R. Adnan, and I. K. Sriwana, “Penentuan Interval Waktu Penggantian dan Perbaikan Komponen Kritis Mesin Bubut Type SS-850 di PT. Hamdan Jaya Makmur Dengan Metode Age Replacement,” J. METRIS, vol. 23, no. 01, pp. 52–61, 2022, doi: 10.25170/metris.v23i01.3547.
J. Guritno and A. S. Cahyana, “Implementasi Autonomous Maintenance Dalam Penerapan Total Productive Maintenance,” Procedia Eng. Life Sci., vol. 1, no. 2, 2021.
I. D. Pranowo, Sistem dan Manajemen Pemeliharaan, Pertama. Yogyakarta: Deepublish, 2019.
T. dan N. Y. A. Ahdiyat, “ANALISIS KINERJA MESIN BANDSAW MENGGUNAKAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) dan SIX BIG LOSSES PADA PT QUARTINDO SEJATI FURNITAMA,” J. Cakrawala Ilm., vol. 2, no. 1, pp. 221–234, 2022.
N. M. Hidayatulloh and T. Sukmono, “Penentuan Interval Perawatan Peralatan Instrumentasi Produksi Pada Industri Kertas,” Product. Optim. Manuf. Syst., vol. 4, no. 1, pp. 23–31, 2020.
L. Hakim, “Implementasi RCM pada mesin diesel Deutz 20 kVA,” J. Progr. Stud. Tek. Mesin UM Metro, vol. 10, no. 1, pp. 42–52, 2021.
A. B. S. dan S. H. Mutiawati, “Usulan Jadwal Preventive Maintenance Komponen Ban,” INTECH Tek. Ind. Univ. Serang Raya, vol. 7, no. 2, pp. 137–146, 2021.
E. A. AGUSTIAWAN, M. Z. FATHONI, and D. WIDYANINGRUM, “Usulan Preventive Maintenance Pada Mesin Hanger Shot Blast Kazo Dengan Menggunakan Metode Age Replacement Di Pt Barata Indonesia,” Matrik, vol. 22, no. 1, p. 73, 2021, doi: 10.30587/matrik.v22i1.2715.
A. B. Zamani, M. Nuruddin, and S. S. Dahda, “Penentuan Interval Penggantian Komponen Mesin Pengayakan Batu Bara Menggunakan Metode Age Replacement,” J. Serambi Eng., vol. VIII, no. 1, pp. 4341–4352, 2023.
F. Fauzi and R. B. Jakaria, “The Implementation of Age Replacement Method for VH-Drum Components for Baby Diaper Production Machines at PT. XYZ,” Indones. J. Innov. Stud., vol. 13, pp. 1–19, 2021, doi: 10.21070/ijins.v13i.526.
R. Pardiyono and P. Suryani, “Meningkatkan Keandalan Komponen Mesin Dan Minimasi Downtime Pada Mesin Picanol Gtx Seri 22844,” Sist. J. Ilm. Nas. Bid. Ilmu Tek., vol. 8, no. 1, pp. 1–8, 2020, doi: 10.53580/sistemik.v8i1.33.
A. Prastiawan, H. Rarindo, E. Hendry, S. Hadi, and U. S. Amrullah, “Metode Rcm Untuk Sistem Perawatan Mesin Amplas Multipleks Pada Pabrik Plywood,” J. Ilm. Teknol. FST Undana, vol. 15, no. 2, pp. 36–40, 2021.
N. dan M. I. M. Ansori, Sistem Perawatan Terpadu (Integrated Maintenance System), Pertama. Yogyakarta: Graha Ilmu, 2013.
J. M. Tupan, B. J. Camerling, and M. Amin, “PENENTUAN JADWAL PERAWATAN KOMPONEN KRITIS PADA MESIN MTU 12V2000G65 DI PLTD TERSEBAR PT PLN (PERSERO) AREA TUAL (Studi Kasus : PLTD Wonreli),” Arika, vol. 13, no. 1, pp. 33–48, 2019, doi: 10.30598/arika.2019.13.1.33.