Analysis of Housing Project Construction Scheduling Using the CPM Method


Analisa Penjadwalan Pembangunan Proyek Perumahan Menggunakan Metode CPM

##article.authors##

DOI:

https://doi.org/10.21070/ups.7601

Keywords:

Critichal Path Method, Microsoft Project, Project Management, Critical Path, Construction Efficiencytemplate

Abstract

PT XYZ, a property company, faces housing construction demand with a unit completion time of 9-12 months. However, 59% of buyers complain about delays in unit handover. This research aims to analyze the scheduling of housing projects using the Critical Path Method (CPM) and Microsoft Project for efficient data processing. The analysis revealed that the project duration decreased from 187 days to 163.5 days, resulting in a labor cost savings of Rp3,215,000. The reduction in time was primarily due to the acceleration of concrete work, although this added 6 days to the masonry work. Critical path analysis identified 31 out of 81 tasks as key elements of the project. This method enabled the concurrent execution of tasks, speeding up the project without raising labor costs, as wages were already budgeted. The optimization focused on efficient worker distribution, ensuring schedule improvement without compromising quality.

Downloads

References

M. A. Jumali and A. Kristina, “Balanced Scored Method : Analisis Pencapaian Strategi Perusahaan Jasa Manufakturing i Pasuruan,” Prozima, vol. 4, no. 1, pp. 32–36, 2020.

I. R. Marodiyah, Inggit, Cahyana, Atikha Sidhi, Nurmalasari, “Jurnal Produktiva INTEGRASI METODE QRM DAN FMEA DALAM MANAJEMEN RISIKO PETANI TEBU,” J. Produkt., vol. 2, no. 3, pp. 1–5, 2022.

Ersin, Syaripuddin, and Q. Q. A’yun, “Aplikasi Penjadwalan Proyek Menggunakan Metode PERT-CPM pada Pembangunan Ruang Kelas SDN 009 Bontang Baru,” BASIS (Jurnal Ilm. Mat., vol. 2, no. 2, pp. 42–54, 2023, [Online]. Available: http://jurnal.fmipa.unmul.ac.id/index.php/Basis/index

N. Saputra, E. Handayani, and A. Dwiretnani, “Analisa Penjadwalan Proyek dengan Metode Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi,” J. Talent. Sipil, vol. 4, no. 1, p. 44, 2021, doi: 10.33087/talentasipil.v4i1.48.

R. Imam, B. Salam, I. Nuryasin, and W. Suharso, “Implementasi Metode CPM dan PERT Pada Proyek Perangkat Lunak Sistem Administrasi Manajemen Pengujian Akhir Semester Kasus ID Core Indonesia,” Repositor, vol. 5, no. 4, pp. 885–894, 2023.

G. P. Arianie and N. B. Puspitasari, “Perencanaan Manajemen Proyek Dalam Menigkatkan Efisiensi dan Efektivitas Sumber Daya Perusahaan (Studi Kasus : Qiscus Pte Ltd),” J@ti Undip J. Tek. Ind., vol. 12, no. 3, pp. 189–196, 2017.

D. Leman and Cindy Paramitha Lubis, “Pemanfaatan Aplikasi Ms. Project Dalam Perencanaan Proyek Pada Pt. Berlian Jaya Mandiri Konsultan,” J-PEMAS - J. Pengabdi. Masy., vol. 4, no. 1, pp. 31–36, 2023.

D. A. Nugroho, T. Sukmono, and R. B. Jakaria, “Analysis of project work using earned value management and precedence diagram method in manufacturing system projects,” Oper. Excell. J. Appl. Ind. Eng., vol. 16, no. 2, pp. 1–15, 2024.

D. Hilman, A. Maskur, and U. Saepudin, “Analisis Penjadwalan Proyek Dengan Program Microsoft Project 2019 (Studi Kasus Proyek Pembangunan Ruang Pelayanan dan Business Centre di SMK Muhammadiyah Kawali),” J. Ilm. Tek. Sipil, vol. 1, no. 1, pp. 11–19, 2023, doi: 10.25157/jiteks.v1i1.3190.

A. F. A. Wicaksono, “Comparison Of The S Curve With The CPM Method In Analyzing Project Scheduling I Nyoman Dita Pahang Putra,” Int. J. Ind. Innov. Mech. Eng., vol. 1, no. 2, pp. 1–12, 2024.

Lilyana, “Analisis Network Planning dengan Critical Path Method (CPM) Dalam Rangka Efisiensi Waktu dan Biaya Proyek Pembangunan Rumah Minimalis (Studi Kasus: Property Group Medan),” J. Sist. Komput. dan Inform. …, vol. 2, no. 1, pp. 80–89, 2020, doi: 10.30865/json.v2i1.2459.

N. M. Astari, A. M. Subagyo, and K. Kusnadi, “Perencanaan Manajemen Proyek Dengan Metode Cpm (Critical Path Method) Dan Pert (Program Evaluation and Review Technique),” J. Konstr., vol. 13, no. 1, pp. 164–180, 2021, doi: 10.24853/jk.13.1.164-180.

Syifa Nur Afiya, Ardana Sultan Alhaq, and Kusnadi, “Analisis penerapan manajemen waktu dengan metode CPM pada proyek pembangunan perumahan griya mahari,” JENIUS J. Terap. Tek. Ind., vol. 4, no. 2, pp. 271–283, 2023, doi: 10.37373/jenius.v4i2.636.

Suherman and A. Ilma, “Analisa Penjadwalan Proyek Menggunakan PDM dan Pert Serta Crash Project (Studi kasus: Pembangunan Gedung Main Power House PT. Adhi Karya),” J. Tek. Ind. J. Has. Penelit. dan Karya Ilm. dalam Bid. Tek. Ind., vol. 2, no. 1, pp. 31–43, 2016, doi: 10.24014/jti.v2i1.5061.

M. N. Sholeh, “Modul Pelatihan Microsoft Project 2019,” 2020, [Online]. Available: https://books.google.com/books?hl=en&lr=&id=tHz4DwAAQBAJ&oi=fnd&pg=PA1&dq=microsoft+project+adalah&ots=s6BNyiE-fq&sig=CXRBiDK9S4rsAXjqh4MhHQOa72w