Overall Equipment Effectiveness (OEE), Six Big Losses, Effectiveness

Abstract

PT. XYZ is a company that has a problem with one of its filling machines experiencing a process failure, resulting in waste. The aim of this research is to analyze the level of machine effectiveness using the overall equipment effectiveness method and identify factors that influence effectiveness by identifying the six big losses and developing strategies to overcome these. The OEE calculation results show a value of 73.748%. This value does not yet reach the standard for the effectiveness of production equipment. The low level of effectiveness comes from losses due to machine damage with a losses value of 9.389% and losses due to equipment operating below standard speed with a losses value of 6.770%. The strategy that needs to be carried out includes making repairs to the punch clamp, filling sensor, and sealer section, as well as carrying out planned maintenance and focused improvement maintenance steps.

Downloads

References

H. C. Wahyuni and S. Setiawan, “Implementasi Metode Objective Matrix (OMAX) untuk Pengukuran Produktivitas pada PT .ABC,” PROZIMA (Productivity, Optimization and Manufacturing System Engineering), vol. 1, no. 1, pp. 17–21, Jun. 2017, doi: 10.21070/prozima.v1i1.702

M. Bahrudin and H. C. Wahyuni, “Pengukuran Produktivitas Kerja Karyawan pada Bagian Produksi dengan Menggunakan Metode Objective Matrix (OMAX) dan Root Cause Analyze (RCA),” PROZIMA (Productivity, Optimization and Manufacturing System Engineering), vol. 1, no. 2, pp. 116–122, Dec. 2017, doi: 10.21070/prozima.v1i2.1299.

W.S. H. C. Wahyuni, Buku Ajar Pengendalian Kualitas Industri Manufaktur dan Jasa. Sidoarjo: UMSIDA Press, 2020.

I. D. Pranowo, Sistem Dan Manajemen Pemeliharaan (Maintenance: System And Management), Pertaman. Sleman: CV Budi Utama. 2019.

D. Sutrisno et al., “Juminten Jurnal Manajemen Industri dan Teknologi Pengukuran Efektivitas Mesin di Lini Produksi Powder Plant PT. Sika Indonesia Menggunakan Metode Overall Equipment Effectiveness dan Six Big Losses”, doi: 10.33005/juminten.v4i1.649.

W. Sukmoro, Sukses Menguasai Implementasi Overall Equipment Effectiveness and M. Produktivitas dan Peningkatan Profitabilitas Bisnis yang Luar Biasa, Demistifikasi PT. Mitra Prima Produktivitas. 2023. [Online]. Available: www.jagokaizen.com

E. Sumarya, J. Batu, A. Baru-Batam-Propinsi, and K. Riau-Indonesia, “Pengukuran Produktivitas dengan Metode Overall Equipment Effectiveness (OEE) untuk Mengetahui Effektivitas Mesin Filling Botol di PT. XYZ The Measurement Of Productivity Using Overall Equipment Effectiveness (Oee) to Indentify Efectiveness Filling Bottle Machine in PT. XYZ,” Profisiensi, vol. 5, no. 2, pp. 98–103, 2017.

I. Nafia et al, “Analisis Produktivitas Mesin Filling Krim pada PT. XYZ dengan Menggunakan Metode Overall Equipment Effectiveness”, Jurnal Bayesian, Vol. 2, No. 1, Maret 2022, 39-46

O. Rabiatussifa et al, “Analisa Produktivitas Mesin Buffing Menggunakan Metode Overall Equipment Effectiveness (OEE) di PT. XYZ Cikarang, Jawa Barat”, Jurnal Ilmiah Wahana Pendidikan, Vol. 8, No. 3, 2022. 95-102.

P. A. Wibowo and I. Padilah, “Analisis Overall Equipment Effectiveness (OEE) dan Six Big Losses pada Mesin Length Adjusment Line 3 Departemen Belt Assy PT. XYZ,” G-Tech: Jurnal Teknologi Terapan, vol. 7, no. 2, pp. 439–449, Mar. 2023, doi: 10.33379/gtech.v7i2.2236.

B. Fadhilah, P. A. Marfinov, and A. J. Pratama, “Overall Equipment Effectiveness (OEE) Analysis to Minimize Six Big Losses in Continuous Blanking Machine,” 2020. [Online]. Available: http://publikasi.mercubuana.ac.id/index.php/ijiem

A. Pandey, “Implemented the Overall Equipment Effectiveness (OEE) by the techniques of Total Productive Maintenance (TPM) in MSE’s-A case study,” 2019. [Online]. Available: www.IJARIIT.com

S. Nakajima, TPM Development Program Implementing Total Productive Maintenance. Cambridge: Productivity Press.1989

H. Ariyah Jurusan Teknik Industri, F. Sains dan Teknologi, U. H. Sultan Syarif Kasim Riau Jl Soebrantas No, and S. Baru, “Penerapan Metode Overall Equipment Effectiveness (OEE) dalam Peningkatan Efisiensi Mesin Batching Plant (Studi Kasus: PT. Lutvindo Wijaya Perkasa),” Jurnal Teknologi dan Manajemen Industri Terapan (JTMIT), vol. 1, pp. 70–77, 2022.

D. Alvira, Y. Helianty, and H. Prassetiyo, “Usulan Peningkatan overall Equipment Effectiveness (OEE) pada Mesintapping Manual dengan Meminimumkan Six Big Losses *,” Jurnal Online Institut Teknologi Nasional Juli, 2015.

R. E. Nugroho and S. Khoirudin, “Overall Equipment Effectiveness Improvement on Cutting Machine by Minimizing Six Big Losses,” Saudi Journal of Business and Management Studies, vol. 05, no. 01, pp. 84–98, Jan. 2020, doi: 10.36348/sjbms.2020.v05i01.011.

M. M. Zulfatri, J. Alhilman, and F. T. D. Atmaji, “Pengukuran Efektivitas Mesin dengan Menggunakan Metode Overall Equipment Effectiveness (OEE) dan Overall Resource Effectiveness (ORE) pada Mesin PL1250 DI PT XZY,” JISI: Jurnal Integrasi Sistem Industri, vol. 7, no. 2, p. 123, Sep. 2020, doi: 10.24853/jisi.7.2.123-131.

D. Wibisono, “Analisis Overall Equipment Effectiveness (OEE) dalam Meminimalisasi Six Big Losses pada Mesin Bubut (Studi Kasus di Pabrik Parts PT XYZ),” Jurnal Optimasi Teknik Industri, vol. 03, no. 01, pp. 7–13, 2021.

S. Priambodo and N. A. Mahbubah, “Implementasi Metode Overall Equipment Effectiveness Berbasis Six Big Losses Guna Mengevaluasi Efektivitas Mesin Packing Semen,” Serambi Engineering, vol. VI, no. 4, 2021.

S. Priambodo and N. A. Mahbubah, “Implementasi Metode Overall Equipment Effectiveness Berbasis Six Big Losses Guna Mengevaluasi Efektivitas Mesin Packing Semen,” Serambi Engineering, vol. VI, no. 4, 2021.

F. Puspa Mellyana, F. Handoko, T. Priyasmanu, Program, and S. T. Industri, “Perhitungan Overall Equipment Effectiveness (OEE) Guna Mengurangi Six Big Losses pada Mesin Produksi dan Usulan Perbaikan Efektivitas Mesin Menggunakan Metode Fault Tree Analysis (FTA) pada PT. MJ,” Jurnal Mahasiswa Teknik Industri), vol. 5, no. 2, 2022.

Fitri Rahmadhani, H. Taroepratjeka, and L. Fitria, “Usulan Peningkatan Efektivitas Mesin Cetak Manual Menggunakan Metode (OEE) (Studi Kasus Di Perusahaan Kerupuk TTN)”,Jurnal Online Institute Teknologi Nasional, Vol. 02, no. 04. 2014

R. Alfatiyah and S. Bastuti, “Improving The Effectiveness Of Primary Rolling Machine With Oee And Six Big Losses Method,” Sintek Jurnal: Jurnal Ilmiah Teknik Mesin, vol. 14, no. 2, p. 85, Dec. 2020, doi: 10.24853/sintek.14.2.85-93.

Posted

2025-02-06