Evaluation of Production Process Scheduling in Order to Improve Optimization Using Genetic Algorithm


Evaluasi Penjadwalan Proses Produksi dalam Rangka Peningkatan Optimasi Menggunakan Algoritma Genetika

##article.authors##

DOI:

https://doi.org/10.21070/ups.540

Keywords:

Styrofoam, First Come First Served, Genetic Algorithm, Makespan

Abstract

PT. Kemasan Ciptatama Sempurna is a company engaged in manufacturing styrofoam.  In companies, there is often a mismatch of the production scheduling system when the number of orders from various customers places orders simultaneously, thus affecting the existing production capacity and resulting in delays in production time. The Genetic Algorithm approach is one of the alternative solutions in fixing problems in scheduling by providing a significant time solution in minimizing the delay in production in terms of scheduling time that has been agreed with the consumer n makespan which provides optimal value production scheduling. The results of this study in production planning obtained a makespan value in the 2021 order activity of 1162.5 hours, this work process uses a genetic algorithm so that a makespan result of 1141.5 hours is obtained. This is more effective than manual scheduling with an efficiency value of 1.02 with a 21-hour savings of makespan.

Downloads

Download data is not yet available.

References

A. Wulandari, “Penerapan Modifikasi Algoritma Genetika Dengan Penambahan Konsep Improvement Dalam Permasalahan Penjadwalan Hybrid Flowshop,” 2018.

L. Amelia and Aprianto, “Optimalisasi Penjadwalan Produksi Dengan Metode Algoritma Genetika Di Pt . Progress Diecast,” InovisiTM, vol. 7, no. 2, pp. 40–46, 2011.

M. Wirahadi, “Elemen Interior Berbahan Baku Pengolahan Sampah Styrofoam Dan Sampah Kulit Jeruk,” J. Intra, vol. 5, no. 2, pp. 144–153, 2017.

R. Kharisma P., E. Ferbrianti, and L. Herlina, “Penjadwalan Produksi Flow Shop Menggunakan Metode Campbell Dudek Smith (CDS) dan Nawaz Enscore Ham (NEH),” J. Tek. Ind. Univ. Sultan Ageng Tirtayasa, vol. 5, no. 3, p. 1432, 2017.

R. Fristha Ayu, “ANALISIS PERENCANAAN PRODUKSI PADA PT. ARMSTRONG INDUSTRI INDONESIA DENGAN METODE FORECASTING DAN AGREGAT PLANNING Fristha Ayu Reicita,” vol. 7, no. 3, pp. 160–168, 2019.

M. I. Fitrianda, “Pengaruh variasi temperature dan holding time pada proses metal injection molding AI/PP terhadap cacat shrinkage,” pp. 1–80, 2013.

D. A. R. Rohmat Taufiq, Rachmat Destriana, Angga Aditya Permana, “Analisis Sistem Penjadwalan Produksi Di Pabrik 1,” Proceeding SENDIU, pp. 978–979, 2021.

R. Christian and D. S. Donoriyanto, “Penerapan Algoritma Genetika Dalam Penjadwalan Mata Kuliah Program Studi Teknik Industri Upn ”Veteran” Jawa Timur,” Tekmapro J. Ind. Eng. Manag., vol. 16, no. 2, pp. 1–12, 2021, doi: 10.33005/tekmapro.v16i2.157.

E. Guanabara, K. Ltda, E. Guanabara, and K. Ltda, PRINCIPLES OF SEQUENCING AND SCHEDULING. .

H. A. Ilhamsah, S. Amar, and N. Irfina, “Perencanaan Penjadwalan Produksi Meminimasi Total Weighted Tardiness dengan Menggunakan Total Weighted Algoritma Genetika,” Semin. Nas. Mesin dan Ind., vol. 9, no. April, pp. 27–29, 2017.

I. Triswara and S. A. veline Anne Marie, “Perancangan Sistem Pengadaan Komponen Perakitan Berdasarkan Material Requirement Planning Dan Penjadwalan Produksi Dengan Metode Algoritma Genetika,” Teknol. dan Sains, vol. 5, no. 1, pp. 1–6, 2019.

A. Zhagi, F. Agustina, D. Bambang, and A. Priatna, “Perencanaan Produksi dan Pengendalian pada Kombinasi Metode MRP dan MILP,” vol. 08, pp. 56–69, 2020, [Online]. Available: https://ejournal.upi.edu/index.php/JEM.

R. D. Apnena, “Optimasi penjadwalan flow shop perusahaan garment dengan metode Campell Dudek Smith, algoritma Nawaz Enscore Ham, dan algoritma Pour dengan kriteria minimisasi makespan,” J. Informatics Electron. Eng., vol. 1, no. 1, pp. 32–35, 2021.

H. Ardiansyah and M. B. S. Junianto, “Penerapan Algoritma Genetika untuk Penjadwalan Mata Pelajaran,” J. Media Inform. Budidarma, vol. 6, no. 1, p. 329, 2022, doi: 10.30865/mib.v6i1.3418.

S. D. Annisya and J. A. Saifudin, “Analisis Penjadwalan Produksi Batu Tahan Api Dengan Menggunakan Metode Campbell Dudek Smith (Cds), Nawaz Enscore Ham (Neh), Dan Palmer Untuk Mengurangi Makespan Di Pt. X,” Juminten, vol. 1, no. 3, pp. 165–176, 2020, doi: 10.33005/juminten.v1i3.119.

A. Alfandianto, Y. A. Nugroho, and W. Setiafindari, “Penjadwalan Produksi Menggunakan Pendekatan Algoritma Genetika di PT Pertani (Persero) Cabang D.I. Yogyakarta,” J. DISPROTEK, vol. 8, no. 2, pp. 1–7, 2017.