Multi-Level Structure of Delay Factors of Entrance Marking Work: Integration of ISM Method and MICMAC Analysis
Struktur Multi-Level Faktor Keterlambatan Pekerjaan Marka Entrance: Integrasi Metode ISM dan Analisis MICMAC
DOI:
https://doi.org/10.21070/ups.10796Keywords:
Constrution, Method Interpretive Structural Modeling (ISM), Delay factor, Project DelaysAbstract
A project can be completed on time according to planning and implementation is very important but it does not rule out the possibility of obstacles in the field that result in delays, by using the Interpretive Structural Modeling (ISM) method, this study aims to determine the factors that trigger project delays in entrance marking work and examine the relationship between these elements. In the JIIPE Manyar Gresik area, this study was conducted at one of the construction companies. The process of interviews and distributing questionnaires to experts with experience in the construction industry was used to collect data, the results of the study found fifteen elements that contributed to the triggers of delays, with drawing errors having the greatest impact (A2). In addition, the results of ISM modeling showed that delay factors were connected in a multi-level structure, with lower-level factors having a greater impact than upper-level elements
Downloads
References
E. C. Halim, A. Andi, and J. Rahardjo, “Aplikasi interpretive structural modeling (ISM) pada faktor-faktor penyebab keterlambatan proyek konstruksi di Surabaya,” Dimens. Utama Tek. Sipil, vol. 8, no. 1, pp. 60–77, 2021.
J. U. D. Hatmoko, A. Hidayat, M. Zachari, and S. S. H. Merukh, “Investigasi Pengaruh Keterlambatan Pembayaran Proyek Konstruksi dari Owner kepada Kontraktor,” TEKNIK, vol. 43, no. 2, pp. 168–177, 2022, doi: https://doi.org/10.14710/teknik.v43i2.45876.
A. Lestari, A. Sandhyavitri, and M. Ikhsan, “Evaluasi Risiko Keterlambatan Pada Proyek Pembangunan Jalan Tol,” ECORINS Proceeding, vol. 1, no. 1, pp. 394–404, 2025.
B. M. C. Kuncoro and T. Octavia, “Analisis faktor-faktor keterlambatan waktu pada proyek konstruksi gedung bertingkat di Indonesia terhadap profesionalisme dan etika kerja,” J. Dimens. Ins. Prof., vol. 2, no. 2, pp. 7–14, 2024.
M. Kapitanhitu, L. M. Saleh, and M. Abdin, “Analisis Faktor Keterlambatan Menggunakan Metode CPM pada Proyek Konstruksi Bangunan Gedung RKB MIN 5 Maluku Tengah,” J. Ilm. Nusant., vol. 2, no. 1, pp. 630–640, 2025, doi: https://doi.org/10.61722/jinu.v2i1.4056.
D. Dwiantoro, A. Y. Yoansa, D. V. Indrayana, S. Mentari, and F. S. Widyatami, “Analisis faktor penyebab keterlambatan proyek ‘XYZ,’” J. Talent. Sipil, vol. 7, no. 1, pp. 388–403, 2024.
S. K. D. Maharani, D. N. Mutmainah, A. H. H. Slamet, and S. Brillyantina, “Penerapan Metode ISM Dalam Menyusun Strategi Pengembangan Usaha Kue Kering CV. XYZ Di Kabupaten Sidoarjo,” Bus. Res. Manag. J., vol. 2, no. 2, pp. 1–29, 2025.
A. S. Cahyana, S. Ainiyah, I. R. Nurmalasari, and I. A. Saidi, “Factors influencing food waste in restaurants and their impact on processing: An interpretative structural modelling approach,” in BIO Web of Conferences, EDP Sciences, 2024, p. 1023. doi: https://doi.org/10.1051/bioconf/202414601023.
S. M. I. Nasution, “Integrasi Prinsip Pengadaan Berkelanjutan dalam Proyek Konstruksi Publik di Indonesia,” JUITECH J. Ilm. Fak. Tek. Univ. Qual., vol. 9, no. 1, pp. 38–49, 2025, doi: http://dx.doi.org/10.36764/ju.v9i1.1606.
S. Hidayat, M. Sayuti, F. Sulastri, and A. Nindiani, “Penggunaan Lean Manufacturing dengan Metode Value Stream Mapping (VSM) dan Failure Mode Effect & Analysis (FMEA) untuk Mengurangi Risiko Kegagalan di PT. SAI,” J. Res. Technol., vol. 11, no. 1, pp. 35–52, 2025, doi: https://doi.org/10.55732/jrt.v11i1.1609.
K. Fahruddin and M. C. P. A. Islami, “Risk Management In The Procurement Process of Upstream Oil Companies Using The House of Risk and Interpretive Structural Modelling,” JATI EMAS (Jurnal Apl. Tek. dan Pengabdi. Masyarakat), vol. 9, no. 1, pp. 115–120, 2025.
B. E. Putra and L. Fitria, “Analisis Prioritas Supplier Susu Freshmilk Menggunakan Metode Interpretive Structural Modelling Dan Analytical Network Process Di Mokopi Garden,” e-Proceeding FTI, 2024.
M. Yusuf and H. Prassetiyo, “Usulan Pemilihan Supplier dengan Menggunakan Metode Interpretive Structural Modelling (ISM) dan Analytical Network Process (ANP) Di PD Sari Tasik,” e-Proceeding FTI, 2022.
D. A. Febriana, F. L. Ardiani, E. Y. Wijaya, and E. Yuliawati, “Analisis Terstruktur Faktor Risiko Operasional Industri Manufaktur Kertas Menggunakan Pendekatan ISM-MICMAC,” J. Rekayasa Ind., vol. 7, no. 2, 2025, doi: https://doi.org/10.37631/jri.v7i2.2008.
I. A. Ahkop, G. J. Johari, and A. S. Pratama, “Analisis Risiko Konstruksi Pada Proyek Pembangunan Gedung Citimall Garut,” J. Konstr., vol. 23, no. 1, pp. 253–264, 2025, doi: https://doi.org/10.33364/konstruksi/v.23-1.1876.
A. V. S. Asmara and A. A. Laksmi, “Analisis Kinerja Waktu Pekerjaan Struktur Atas Proyek Rumah Sakit X di Jakarta Selatan,” J. Tek. Sipil, 2025, doi: https://doi.org/10.21009/jmenara.v20i2.54388.
A. K. Khotimah and M. Beatrix, “Analisis Faktor Keterlambatan Waktu Pelaksanaan Proyek Jalan Nasional di Jawa Timur,” J. Tek. Sipil, vol. 15, no. 2, pp. 48–59, 2022.
L. Kopong, N. Maelissa, and H. D. Titaley, “Faktor-Faktor Penyebab Keterlambatan Proyek Renovasi Dan Perluasan Gedung Balai Karantina Ikan Ambon,” J. Agreg., vol. 2, no. 2, pp. 122–129, 2023, doi: https://doi.org/10.31959/ja.v2i2.1200.
J. U. D. Hatmoko, R. A. Pratistha, and A. Hidayat, “Keterlambatan proyek yang disebabkan oleh owner: Evaluasi faktor-faktor penyebab dan klaim kontraktor,” Media Komun. Tek. Sipil, vol. 28, no. 2, pp. 212–218, 2022, doi: https://doi.org/10.14710/mkts.v28i2.45875.
E. Azhari, L. M. Saleh, and M. Marantika, “Analisis faktor penyebab keterlambatan proyek pembangunan gedung laboratorium terpadu dan perpustakaan MAN 1 Maluku Tengah,” J. Agreg., vol. 2, no. 2, pp. 262–270, 2023, doi: https://doi.org/10.31959/ja.v2i2.1906.
A. Imran, M. Alamsyah, and T. H. Nugroho, “Analisis Faktor Penyebab Keterlambatan Proyek Konstruksi di Nunukan,” axial J. rekayasa dan Manaj. Konstr., pp. 232–239, 2025, doi: https://doi.org/10.30742/axial.v13i3.5021.
M. M. Sanaky, “Analisis faktor-faktor keterlambatan pada proyek pembangunan gedung asrama MAN 1 Tulehu Maluku Tengah,” J. simetrik, vol. 11, no. 1, pp. 432–439, 2021, doi: https://doi.org/10.31959/js.v11i1.615.
S. E. Priana and J. Hafnil, “Analisis Faktor Penyebab Keterlambatan Proyek Konstruksi (Studi Kasus: RSI Ibnu Sina Padang Panjang),” J. Rangkiang, vol. 1, no. 1, pp. 50–58, 2025.
K. Fahruddin and F. Pulansari, “Analisis Risiko Rantai Pasok Peternakan Ayam Petelur Menggunakan House of Risk dan Interpretive Structural Modelling,” J. Samudra Ekon. dan Bisnis, vol. 17, no. 225, pp. 29–44, 2026, doi: 10.33059/jseb.v17i1.11719.Article.
M. A. Indrianti, I. Taslim, and M. M. Djibran, “Strategi Implementasi Kebijakan Perlindungan Lahan Pertanian Pangan Berkelanjutan : Strategy For Implementing The Policy for Protecting Sustainable Food Agricultural Land,” in Prosiding Seminar Nasional Integrasi Pertanian dan Peternakan, 2026, pp. 293–300.
N. Martani and I. N. Pujawan, “Critical Success Factor terhadap Penerapan Sustainable Supply Chain pada Sektor Perikanan dengan Pendekatan PCA-ISM,” Fact. J. Ind. Manaj. dan Rekayasa Sist. Ind., vol. 4, no. 3, pp. 394–408, 2026, doi: https://doi.org/10.56211/factory.v4i3.1592.
T. Harefa, Y. Lubis, and T. Martial, “Analisis Kebijakan Usaha Perkebunan Kelapa Sawit Dengan Penggunaan Pupuk Limbah Pabrik,” Jesya (Jurnal Ekon. dan Ekon. Syariah), vol. 8, no. 1, pp. 736–750, 2025, doi: 10.36778/jesya.v8i1.2012.
T. Wakhyudi, M. Sayuti, and K. Karnadi, “Analisis mitigasi risiko kecelakaan kerja Divisi AC pada perusahaan elektronik di Karawang dengan menerapkan metode HOR dan ISM,” J. Integr. Syst., vol. 7, no. 1, pp. 83–97, 2024, doi: https://doi.org/10.28932/jis.v7i1.9154.
B. W. D. LEGOWO and L. FITRIA, “Usulan Pemilihan Supplier Kopi Menggunakan Interpretive Structural Modeling (ISM) dan Analytical Network Process (ANP) pada Mokopi Cimindi,” e-Proceeding FTI, 2024.
A. B. Saraswati, C. Farela, M. Tantrika, and R. A. Sari, “Identifikasi Dan Penanganan Risiko Operasional Penyebab Keterlambatan Proyek Pembuatan Kapal Dengan Pendekatan Analytical Hierarchy Process (AHP),” J. Rekayasa Sist. Manaj. Ind., vol. 02, no. 02, pp. 190–198, 2025.
A. E. Susanto and H. Wiyanto, “Analisis Pengaruh Keterlambatan Proyek Terhadap Estimasi Biaya Dan Waktu Penyelesaian Proyek X Di Sawangan,” JMTS J. Mitra Tek. Sipil, vol. 8, no. 1, pp. 51–62, 2025, doi: https://doi.org/10.24912/jmts.v8i1.32613.
N. I. Arini, “Rancangan Perbaikan Gudang Persediaan di CV Kina Citratama Dengan Metode Fishbone,” J. Ind. Furnitur dan Pengolah. Kayu, vol. 3, no. 2, pp. 59–68, 2025.
M. Syihabuddin and P. A. Tuti, “Studi Eksploratif Tentang Praktik Sistem Manajemen Persediaan Dan Perencanaan Material Dalam Meningkatkan Efisiensi Proyek Konstruksi Di PT Sekawan Jaya,” JAZ J. Akunt. Unihaz, vol. 8, no. 2, 2025, doi: https://doi.org/10.32663/nr8rvr74.