Analysis Of Project Work Using Earned Value Management and Precedence Diagram Methode In Manufacturing System Project


Analisis Pengerjaan Proyek Menggunakan Earned Value Management dan Precedence Diagram Methode Pada Proyek Sistem Manufaktur

##article.authors##

DOI:

https://doi.org/10.21070/ups.5048

Keywords:

Earn Value Management, Precedence Diagram Methode, MS Project

Abstract

PT. Weiss Tech has received a project has been ongoing for 16 weeks with an update indicating that only 20% of the planned progress has been achieved, which suggests that it may not be completed on time. Evaluation Earned Value Management method shows negative values for CV and SV variances, as well as performance index SPI < 1 and CPI < 1, indicating poor project performance. The critical tasks identified include electrical & instrument installation, machine & utility installation, trial work, assembly, quality control, polishing, milling, turning, cutting, and design. Design work has been identified as the most influential on the critical path. By rescheduling the project plan, positive values for CV and SV have been achieved. With the SPI value of 1.13 and CPI value of 1, it can be concluded that future project performance will be completed faster and within budget

Downloads

Download data is not yet available.

References

M. Caintan and Suwarno, “Computer Based Information System Journal Perancangan dan Pengembangan Aplikasi Pendukung Proses Manufaktur dalam Penyusunan Palet Menggunakan Metodologi Prototyping,” CBIS JOURNAL, vol. 10, no. 01, Mar. 2022, [Online]. Available: http://ejournal.upbatam.ac.id/index.php/cbishttp://ejournal.upbatam.ac.id/index.php/cbis

R. D. Wisesa and Purwandari, “Pengaruh Penerapan Media Pembelajaran Otomasi Industri Berbasis Arduino Mega 2560 pada Mata Kuliah Elektromekanik terhadap Kemampuan Pemahaman Konsep dan Psikomotorik Mahasiswa,” vol. 05, pp. 12–18, 2021.

G. Dinata, A. Muttaqin, and M. Darsin, “RANCANG BANGUN DAN UJI PERFORMASISTEM KENDALI PEMBERIAN FLUIDA PERMESINAN MQL BERBASIS ARDUINO,” REKAYASA MESIN, vol. 11, pp. 97–104, 2020.

M. Farrel Ghiffary, F. Abdul Mukti, A. Zulfa Geofani Firdaus, T. Nugroho Sulistyantoro, and M. Farrel Ghiffary Muhammadfarrelghiffary, “Analisis progres realisasi proyek terhadap biaya pada proyek jembatan kereta api rangka baja Surakarta,” Proceeding Civil Engineering Research Forum, vol. 3, pp. 63–71, 2023.

E. S. Ginting, D. Charin, and N. Tarigan, “Penjadwalan Produksi Celana Katun Menggunakan Metode Heuristic Pour,” EE Conference series, pp. 178–181, 2023, doi: 10.32734/ee.v6i1.1802.

S. Supardi, A. Ahmadsyah, J. Urip Sumoharjo Km, K. Panakkukang, K. Makassar, and S. Selatan, “Tinjauan Waktu Pelaksanaan Proyek Menggunakan Microsoft Project 2021 pada Pembangunan Pesantren Entrepeneurship Kabupaten Lebak Provinsi Banten,” Teknik Sipil, vol. 8, pp. 159–169, 2021.

X. Furuhitho et al., “Perencanaan Pengendalian Biaya dan Waktu pada Proyek Pembangunan Rumah Susun Stie Tazkia Cendikia Bogor dengan Metode Earned Value,” Journal Of Social Science Research, vol. 3, pp. 7591–7600, 2023.

K. Reski Meliya, D. Purnama Sari, M. Arrie Rafshanjani, and H. Artikel, “Evaluasi Pelaksanaan Pembangunan Proyek Dengan Menggunakan Metode Earnede Value Informasi Artikel,” Jurnal Ekonomi – Teknik, vol. 1, pp. 374–382, 2022.

J. Veronika and B. Ginting, “Metode Earned Value Pada Pengendalian Proyek Pembangunan Gedung Sekolah SD Methodist-an Pancur Batu,” Journal of Economics and Accounting, vol. 1, pp. 6–10, 2020.

W. Proboretno, B. Witjaksana, and H. T. Tjendani, “ANALYSIS OF COST AND TIME PERFORMANCE IN THE WADUNGASRI MARKET CHANNEL NORMALIZATION WORK IN SIDOARJO USING THE EARNED VALUE METHOD,” INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, vol. 3, no. 2, 2024, [Online]. Available: https://ojs.transpublika.com/index.php/IJATEIS/

C. Luntungan, T. T. Arsjad, and J. B. Mangare, “Analisis Penjadwalan Proyek Dengan Metode Precedence Diagram Method (PDM) Menggunakan Konsep Cadangan Waktu Pada Proyek Pembangunan Jembatan Sosongian Minahasa Selatan,” Tekno, vol. 21, no. 85, pp. 1690–1698, 2023.

M. R. Mantovani and M. Beatrix, “EVALUASI PENGENDALIAN BIAYA DENGAN METODE CRITICAL PATH METHOD (CPM) MENGGUNAKAN MICROSOFT PROJECT (STUDI KASUS: PEKERJAAN TAHAP VII PROYEK PERKUATAN STRUKTUR DERMAGA BERLIAN TANJUNG PERAK SURABAYA),” Jurnal Ilmiah Teknik dan Manajemen Industri, vol. 3, no. 1, pp. 2023–721, doi: 10.46306/tgc.v3i1.

M. Irfan, H. Ahadis, I. Haryono, and I. A. Puspita, “PENGUKURAN KINERJA WAKTU PROYEK MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) DAN MENGOPTIMALKAN WAKTU PROYEK MENGGUNAKAN PRECEDENCE DIAGRAMMING METHOD (PDM) PADA PROYEK RENOVASI RUANGAN PT. XYZ,” e-Proceeding of Engineering, vol. 7, pp. 5521–5527, 2020.

S. Nalawade, O. Ghode, and P. Vaidya, “Earn value analysis of construction project using primavera p6,” CIKITUSI JOURNAL FOR MULTIDISCIPLINARY RESEARCH, vol. 6, no. 5, pp. 514–522, 2019, [Online]. Available: http://cikitusi.com/

K. Reski Meliya, D. Purnama Sari, M. Arrie Rafshanjani, and H. Artikel, “ETNIK : Jurnal Ekonomi-Teknik Evaluasi Pelaksanaan Pembangunan Proyek Dengan Menggunakan Metode Earnede Value Informasi Artikel,” Ekonomi Teknik, vol. 1, pp. 374–382, 2022.

Project Management Institute and Agile Alliance, A guide to the project management body of knowledge (PMBOK guide). 2017.