Comparative Analysis of Construction Time and Cost Efficiency between PU Sandwich Panel Walls and Hebel Concrete Walls Using the Integrated Project Performance Measurement (IPPM) Method

Analisis Perbandingan Efisiensi Waktu dan Biaya Konstruksi antara Dinding Sandwich Panel PU dan Dinding Beton Hebel Menggunakan Metode Integrated Project Performance Measurement (IPPM)

##article.authors##

DOI:

https://doi.org/10.21070/ups.10211

Keywords:

PU Sandwich Panel, Hebel Concrete (AAC), cost and time efficiency, Integrated Project Performance Measurement (IPPM), CPI–SPI–IPPI

Abstract

This study evaluates the cost and time efficiency of Polyurethane (PU) Sandwich Panel and Hebel concrete wall systems in two operator room projects in Sidoarjo using the Integrated Project Performance Measurement (IPPM) method. In Operator Room 1, the actual cost of PU panels increased by 14.29% to Rp18,480,000, while Hebel concrete showed cost overruns with a CPI of 1.17. In Operator Room 2, both systems met planned budgets at Rp25,060,000 for PU and Rp14,456,000 for Hebel. In terms of schedule, PU panels achieved acceleration of 20–33%, whereas Hebel concrete experienced delays of up to 25%. IPPI values confirm that PU panels outperformed Hebel in integrated performance, scoring 1.19 and 1.13 versus 0.83 and 0.92. Overall, Hebel is more economical in nominal cost, while PU panels provide superior cost–time efficiency.

Downloads

Download data is not yet available.

References

E. Mulyati et al., Smart Construction: Transformasi Digital Dalam Manajemen Proyek. CV. Gita Lentera, 2025.

M. B. Masgode et al., Dinamika Industri Konstruksi di Indonesia. Tohar Media, 2024.

B. L. Al Zakina, Dinding Ringan Tahan Gempa: Inovasi Panel EPS-Kalsiboard untuk Rumah Aman dan Nyaman. PT Penerbit Qriset Indonesia, 2025.

K. Anugerahanto and G. A. Y. P. Adistana, “Perbandingan Pelaksanaan Pekerjaan Dinding Precast dan Dinding Konvensional pada Konstruksi High RIse Building Ditinjau dari Segi Waktu dan Biaya,” Rekayasa Teknik Sipil, vol. 9, no. 4, 2021.

F. F. Ximenes, “Analisis Waktu Dan Biaya Dalam Pengendalian Proyek Konstruksi Menggunakan Metode Earned Value: Studi Kasus Proyek Gedung UNTL,” axial: jurnal rekayasa dan manajemen konstruksi, vol. 13, no. 1, pp. 11–20, 2025.

H. A. Siva and I. Junita, “Evaluasi Kinerja Proyek Perumahan Rakyat di Kabupaten Bandung Barat dengan Menggunakan Earned Value Management (EVM) dan Visualisasi Kurva ‘S,’” Journal of Integrated System, vol. 8, no. 1, pp. 75–88, 2025.